Malibu Rebuild Timeline: How Long Does It Take After a Fire?

Malibu Rebuild Timeline: How Long Does It Take After a Fire?

  • Bill & Daniel Moss
  • 01/20/26

The days following a wildfire can be some of the most challenging a homeowner will ever face, especially when looking out over a property in a beautiful area like Point Dume or the Malibu Park hills. The Malibu rebuild timeline is a marathon, not a sprint, and understanding the steps now can help you make the best decisions for your family and your investment.

Key Takeaways

  • A detailed breakdown of the five critical phases of rebuilding, from debris removal to the final certificate of occupancy.

  • Insights into expedited permitting options for "like-for-like" projects compared to custom estate designs.

  • Current 2026 city deadlines for fee waivers and permit applications to help you maximize your financial recovery.

  • Expert tips on coordinating with design professionals and contractors to keep your project moving forward.

Phase One: Damage Assessment and Debris Removal

Before the first new brick can be laid, your site must be cleared and certified as safe by the County of Los Angeles and the City of Malibu. 

Immediate Steps for Site Readiness

  • Insurance Documentation: We suggest taking thorough photos and videos of the damage before any debris is moved to ensure your claim reflects the full value of your loss.

  • Hazardous Waste Sweep: Phase 1 of debris removal always involves a government-led sweep for household hazardous waste, which usually takes about 28 to 45 days.

  • Soil Testing and Certification: Once the visible debris is gone, the soil must be tested for toxins to ensure the site is environmentally safe for a new residence.
This phase typically moves quickly but is essential for establishing the foundation of your insurance claim and your future post-fire construction process.

Phase Two: The Design and Engineering Stage

Once your site is cleared, the LA custom home schedule truly begins with the engagement of an architect and structural engineers.

Coordinating Your Professional Team

  • Licensed Architects: We make sure our clients hire architects who are intimately familiar with the Malibu Local Coastal Program (LCP) to avoid design revisions later.

  • Geotechnical and Coastal Engineers: Hillside and beachfront lots often require specialized reports to verify soil stability and seawall integrity before plans can be submitted.

  • Onsite Wastewater Treatment Systems (OWTS): Because most of Malibu relies on septic systems, a City-registered practitioner must inspect and often redesign your system to meet modern standards.
Whether you are rebuilding a modern masterpiece on Broad Beach or a rustic canyon retreat, your design team must account for updated building codes that have likely changed since your original home was constructed.

Phase Three: Navigating the Permitting and Plan Check

Securing permits is traditionally the most time-consuming part of the Malibu rebuild timeline, often taking anywhere from six months to over a year for custom projects. However, the City of Malibu offers expedited tracks for those choosing to build "like-for-like" or "like-for-like plus 10%." 

Key Deadlines for 2026 Homeowners

  • Building Permit Deadlines: For those affected by previous fires, such as the Woolsey Fire, the deadline to obtain building permits to maintain non-conformities is currently November 8, 2026.

  • Fee Waiver Program: The City Council has extended the fee waiver program for "like-for-like" primary residences through December 30, 2026, which can save homeowners tens of thousands of dollars.

  • Coastal Development Permits (CDP): If you are increasing your home's size by more than 10% or moving its location, a full CDP is required, which typically takes 12 to 24 months for approval.
These options can significantly shorten your review timeframe, sometimes reducing it to just a few weeks or months if you are using pre-approved standard plans or staying within the original footprint.

Phase Four: The Construction and Inspection Journey

This phase is the largest portion of the timeline, typically spanning 12 to 24 months for a high-end custom estate in Malibu.

Maintaining Progress on the Job Site

  • Foundation and Framing: These early stages are critical; if you are reusing an existing foundation, it must undergo destructive core testing to confirm its structural strength.

  • Utility Installation: Coordinating with Southern California Edison and local water districts early is the top priority to ensure your home is ready for occupancy as soon as the build is complete.

  • Continuous Communication: We suggest regular site meetings with your builder to monitor the LA custom home schedule and address any material lead-time issues immediately.
Throughout this period, the City will conduct a series of inspections to ensure that the work aligns with the approved plans and meets the latest fire-resistant building codes, including the use of non-combustible siding and specialized roofing materials.

Phase Five: Final Inspection and Moving Back Home

The final few weeks of your rebuild involve a series of comprehensive checks by the Building Safety Division and the Fire Marshal. 

The Final Hurdles to Occupancy

  • Fire Department Sign-Off: The LA County Fire Department must verify that your "defensible space" landscaping meets the latest brush clearance ordinances.

  • OWTS Operating Permit: You must obtain your final operating permit for your septic system within 60 days of receiving your Certificate of Occupancy.

  • Final Walkthrough: Use this time to ensure every detail of your luxury finish work meets the high standards you established at the beginning of the project.
This is the moment you have been working toward, allowing you to finally return to your community and enjoy the incomparable Malibu lifestyle once again.

FAQs

How long does a typical "like-for-like" rebuild take in Malibu?

For a "like-for-like" project with expedited permitting, you can realistically expect a total timeline of 18 to 24 months from the fire event to moving back in.

Can I change the design of my home without losing expedited permitting?

The City offers a "like-for-like plus 10%" option, which allows for a 10% increase in height, square footage, or volume while still qualifying for a faster Planning Verification process.

What happens if I miss the 2026 building permit deadlines?

If you miss the November 8, 2026, deadline for certain fire rebuilds, you may lose the right to maintain "legal non-conformities," such as old setbacks or height limits.

Reach Out to Bill & Daniel Moss Today

Whether you are looking to purchase a "burn lot" with approved plans or need guidance on your current project, we have the "boots-on-the-ground" knowledge to help you succeed.

Reach out to us at Bill & Daniel Moss, and we will help you navigate the nuances of the Malibu luxury market with the precision and care you deserve.